Glade Run Development Updates
Update 10/4/24
The Developers continue the grading and erosion control for Phases One and Two. The project is moving forward with sewer, storm water management, paving, and then utilities, with hopes of the construction of a few model homes by the end of 2024.
The roads are being graded and developed for both phases. Included in this update is an illustration depicting the layout of the future placement of the streets for the entire development. There will be two access points, one connecting Oakdale Drive, and the other is the main entrance from Route 68. These have not changed from the approved plans originally submitted.
With the grading work in Phase One and Two, there has been continuous movement of earth. The transfer of dirt in the dry conditions began to stir up dust. The Developers are spraying the ground with water to minimize the dust.
A project of this stature continues to be vastly complex. There has been good communication between the entities involved. Zelienople Borough will continue to provide important updates through the borough website.
Please direct any questions or concerns to the Zelienople Zoning Officer, Jason Sarver at jsarver@zelieboro.org or 724.452.3002.
Click here to view the development illustration.
Update 7/10/24
The Developers have started with the mowing and grading of earth and erosion control for Phases One and Two. This is generally followed up with sewer, storm water management, paving, and then utilities.
The Developers will try to minimize removing trees within the buffer zone as much as possible, where they do have to remove any trees, they will plan on replanting.
With the grading work in Phase One and Two of the areas depicted, they will be removing dirt. The future houses will be sitting lower than the existing ground, which means that we will be planting the trees on the top portion of the slope and closer to the affected properties. This should provide the maximum amount of buffering with the trees. Expect the Developers to be grading the eastern portion of the project, the week of July 15th.
A project of this stature is vastly complex, with a lot of moving parts. There has been good communication between the entities involved. Zelienople Borough will continue to provide important updates through the borough website.
Please direct any questions or concerns to the Zelienople Zoning Officer, Jason Sarver at jsarver@zelieboro.org or 724.452.3002.
Buffer Planting Exhibit Glade Run Phasing Exhibit